Surčin field plan of about 26 hectares enters public review

Public review of a draft plan covering about 26.36 hectares of farmland near Surčin and Dobanovci began on 23 November 2026 for a BEXEXPRESS mail centre, new roads and commercial sites.

A draft detailed regulation plan for part of a business zone beside the bypass freight railway near Surčin has entered public review. It covers about 26.36 hectares, mostly in the cadastral municipality of Dobanovci, with a smaller part in the cadastral municipality of Surčin, close to Dobanovci and the freight line.

The planning documents state that the plan was prompted by an initiative from BEXEXPRESS of Šabac, which is also the client for the plan. The aim is to set rules for arranging and building an express-mail centre with warehouse capacity, supporting buildings, and the handling and traffic areas the company needs.

The area is divided into four economic zones and two commercial zones. The economic part provides for warehouses with supporting facilities, space for other economic activities, car showrooms and service workshops with technical inspection, and a BEXEXPRESS express-mail distribution centre in a separate zone marked P4. One commercial area is intended for charging stations for electric passenger and freight vehicles. The other is for supplying vehicles with compressed natural gas, together with compressor stations. Business, production, warehouse and service buildings, and the infrastructure needed to run them, are also allowed in the economic zone.

Five new roads would link the separate economic and commercial areas with Železnička Street, state road II B number 319. The central road, marked Nova 5, would give access to the economic zones on both sides, including the planned express-mail centre. The remaining roads would connect this part of the business zone with Železnička Street. Each new road is planned with a carriageway seven metres wide and sidewalks on both sides.

The plan also includes widening the Železnička Street carriageway to two traffic lanes in each direction, in line with an earlier planning solution. Because of that widening, the existing bus stop toward Dobanovci would be moved, while the stop toward Surčin would keep its present position. Existing utility installations and parking areas lying in the future carriageway would have to be relocated.

The planning documents say the area currently has no functioning public sewer for wastewater. A sewer is planned along all five new roads, connecting to a future collector 700 millimetres in diameter in Železnička Street. Further removal of wastewater would depend on development of the Batajnica sewer system, some of whose structures are planned in separate documents. Until a functioning public sewer is built, the plan allows temporary disposal through watertight collection pits, or septic pits, on the plots. After the public network is built, buildings would have to connect to it and the temporary systems would be taken out of use. Rainwater from traffic, handling and parking surfaces would be collected and treated and would have to pass through settlers and grease and oil separators before discharge. Water-supply and electricity networks are also planned so the land can be equipped for the business and commercial uses.

According to the planning documents, the site is undeveloped and is used mostly as agricultural land. The parcels are recorded as second-class fields, and corn and wheat are grown on some of them. Compared with an earlier study, the routes of four planned roads were corrected while the draft was prepared, which also extended the plan boundary. The Plans Commission of the Belgrade City Assembly accepted those departures on 3 November 2026.

Almost 37,800 square metres is planned as a protective green belt inside the protection zone of Nikola Tesla Airport. Low vegetation is envisaged there, in line with the limits that apply near the airport.

On the same day, councillors of the Belgrade City Assembly adopted the Spatial Plan for part of the city municipality of Surčin, phase I, which also covers planning arrangements for the villages of Petrovčić, Bečmen, Progar and Boljevci. They also adopted a separate detailed regulation plan for part of the Surčin–Dobanovci business zone. Those documents are separate from the draft for the business zone beside the bypass freight railway that provides for the BEXEXPRESS centre. The express-mail documents state that the coverage of the two business-zone plans partly overlaps along Železnička Street, in the area of the planned junction.

Public inspection of the draft runs from 23 November 2026 to 4 January 2027. The documents are available at the Belgrade Urban Planning Institute, Bulevar despota Stefana 56, and at the Surčin city municipality building, Vojvođanska 79, on every working day from 09:00 to 18:00. Citizens and legal entities may send written comments to the Secretariat for Urban Planning and Construction Affairs at Kraljice Marije 1, up to and including 4 January 2027. A public session of the Plans Commission, where people who submitted comments can explain them, is set for 19 January 2027 at 13:00 in the City Administration building at 27. marta 43–45.

Surčin farmland plan · Dobanovci business zone · BEXEXPRESS distribution centre · corn and wheat fields · Belgrade public review · Železnička Street widening · Serbia agriculture and farming